Facebook icon
Hospitals 28 February 2023

Frankston Hospital redevelopment - Newsletter #1 | Feb 2023

Welcome to our first project newsletter!

We’ll be issuing these newsletters regularly to keep you informed of exciting progress on the site and to introduce you to some of the people working behind the scenes to deliver the bigger and better Frankston Hospital.

Frankston Hospital redevelopment - construction update March 2023

IMAGES: Aerial footage of the Frankston Hospital redevelopment site showing machinery in operation on the site.

TEXT: Construction is well underway on the site of the Frankston Hospital redevelopment.

IMAGES: Bird’s-eye view of the construction site and close-up of a piling rig being lifted.

TEXT: Foundations are progressing, with 320 foundation and retention piles installed.

IMAGES: Aerial footage of activity on construction site. Footage of a large concrete pipe being moved.

TEXT: We have installed 2.3 kilometres of piping under the site.

IMAGES: Close up and overheard views of an excavator digging and pouring earth into a truck.

TEXT: moved around 112,000 cubic metres of soil – enough to fill around 40 Olympic swimming pools.

IMAGES: Construction workers smoothing out asphalt using small machinery.

TEXT: and used over 5,500m2 of asphalt to prepare the temporary car park.

IMAGES: Timelapse footage of foundation works. Close-ups of construction workers smoothing asphalt.

TEXT: More than 240 people have been inducted onto the site, with more than 64,000 hours of work completed.

IMAGES: Aerial shot of the construction site.

TEXT: Construction of main works on your bigger and better Frankston Hospital is expected to be complete in 2025.

IMAGES: A closing slide says: ‘In partnership with’ and has the Peninsula Health and Exemplar Health logos. This fades into another slide with the Victorian Health Building Authority and Victorian Government logos. The URL vhba.vic.gov.au is displayed.

End of transcript.

Progress in 2022

Redeveloping a working hospital is a complex job, but significant progress has been made since major construction started in June 2022.

So far, we have:

  • installed 320 foundation and retention piles
  • installed 2,300 lineal metres of piping under the site
  • moved around 112,000 cubic metres of soil - enough to fill around 40 Olympic swimming pools
  • used over 5,500 square metres of asphalt to prepare the temporary car park
  • inducted more than 240 people onto the site, with more than 64,000 hours of work completed.
Three images showing stages of construction on the Frankston Hospital redevelopment site in 2022. 1. Site demolition. 2. Aerial view of cleared site. 3. Aerial view of new temporary carpark

  • Step 1
    Construction site cleared
    Step 1
    Construction site cleared
  • Step 1
    Diversion of inground services Including high-voltage power to the hospital
    Step 1
    Diversion of inground services
    Including high-voltage power to the hospital
  • Step 1
    Temporary site amenities Including fencing and hoarding set up
    Step 1
    Temporary site amenities
    Including fencing and hoarding set up
  • Step 1
    Temporary carpark constructed 184 parking spaces that will remain until the new multideck carpark opens
    Step 1
    Temporary carpark constructed
    184 parking spaces that will remain until the new multideck carpark opens
  • Step 1
    Foundation and retention piling works
    Step 1
    Foundation and retention piling works
  • Step 5
    New bus stop on High Street The first of three stops has a shelter, seating and solar lighting
    Step 5
    New bus stop on High Street
    The first of three stops has a shelter, seating and solar lighting
  • Step 1
    Installation of temporary project offices next to the Croquet Club
    Step 1
    Installation of temporary project offices next to the Croquet Club
  • Step 1
    Emergency department refurbishment works begin Please note that the emergency department will remain open at all times
    Step 1
    Emergency department refurbishment works begin
    Please note that the emergency department will remain open at all times
  • Step 1
    Four tower cranes arrive on site
    Step 1
    Four tower cranes arrive on site
  • Step 1
    Foundation works complete
    Step 1
    Foundation works complete
  • Step 1
    Works on new multideck carpark
    Step 1
    Works on new multideck carpark
  • Step 1
    Start of construction on the main tower
    Step 1
    Start of construction on the main tower
  • Step 5
    Construction of main works on track for completion in 2025
    Step 5
    Construction of main works on track for completion in 2025

How we work

Like any major project, some disruption is to be expected. We are working hard to minimise any impacts for our project neighbours, patients and staff and to provide updates to the community as construction of the redevelopment progresses.

Some of the measures we implement include:

  • scheduling extra street sweepers on surrounding roads to minimise dirt spread by trucks
  • spraying water over the site when large amounts of dirt are being moved to minimise dust
  • operating machinery within the Environment Protection Authority's noise guidelines and, where possible, using quieter options to minimise noise for patients, staff and neighbours.

At times, traffic management will be in place to keep pedestrians and road users safe as machinery and trucks enter and exit the site. Please stay alert and follow the signage in place as directed.

" "

How do we design a redevelopment?

An expert team including architects, designers, engineers, and cultural and heritage specialists are working hard to ensure the design meets the needs of all patients, staff, and visitors to the hospital.

Community members have helped to shape the redevelopment through the public consultation process - over 580 contributions were captured through online forums, surveys and workshops.

Groups of Peninsula Health staff and consumer representatives are involved in detailed design meetings to plan the location, size and layout of rooms in the new tower. Once the layout is finalised, they will focus on the finer details including equipment requirements, locations of switches, hooks, handrails, and interior finishes.

More than 65 user groups and 70 staff reference group meetings have been completed as part of the first stage of design. The second stage of the detailed design will be finalised in late 2023.

Meet the faces of Frankston Hospital

Sreyurs Kesavan Sreedhar

Nurse Unit Manager (Emergency department)

'The best thing about working in Peninsula Health is the fact that you’ll be helping people every single day, whilst making a positive impact on their life. Peninsula Health is very inclusive and support you to excel in your pathway. I always wanted to work with an organisation that prioritises patient centred care.

'My job involves managing and supporting my team which includes nurses, clerical staff, physiotherapists, and occupational therapists every day. I also must ensure that the team have all the resources and capability to provide safe, personal, effective, and connected care to our patients.'

Photo of Frankston Hospital Nurse Unit Manager Sreyurs Kesavan Sreedhar

'I am looking forward to the new dedicated paediatric emergency unit which will be an expansion of the current unit with additional beds. This will enhance our capability to provide care for our paediatric patients. The expansion and redevelopment of our waiting room is also exciting.'

A greener hospital

Artist impression showing landscaping with people walking along a pathway and sitting on benchesMore than 200 new trees and extensive vegetation will be planted as part of the landscape design for the redevelopment.

The new landscape will include:

  • 20,000m2 of new open space
  • 10,000m2 of planted gardens
  • 6,900m2 of canopy cover
  • more than 60 roof decks, balconies, winter gardens and courtyards.

Delivering your redevelopment

The Exemplar Health consortium is delivering the project with the Victorian Government as part of a public private partnership (also known as a PPP).

Exemplar Health will design, construct, finance, and maintain the new facility for 25 years. The consortium brings together:

  • Capella Capital as sponsor and investor
  • Aware Super as investor
  • Lendlease as design and construction contractor
  • Honeywell and Compass Group Australia as facilities services providers.

Frankston Hospital will continue to be a public hospital, operated by Peninsula Health.

" "

Find out more

Further information on the Frankston Hospital redevelopment is available on our dedicated project page.

Have a question?

If you have any questions about the construction of the Frankston Hospital redevelopment, you can contact:
Exemplar Health
Phone: 1800 00 36 77
Email: enquiries@exemplarhealthfhr.com.au.

If you have any questions about hospital operations, you can contact:
Peninsula Health
Email: fhredevelopment@phcn.vic.gov.au

Acknowledgement of Country

The Frankston Hospital redevelopment project acknowledges the Boon Wurrung/Bunurong people of the Kulin Nation, the Traditional Custodians of the lands on which the hospital sits and pay our respects to their Elders, past and present.

Subscribe and stay up-to-date

" "

Stay up-to-date on our announcements and projects by signing up to our online newsletters.
 

Subscribe

Related content

Artist impression of aerial view of the Frankston Hospital Redevelopment

17 October 2019

Frankston Hospital redevelopment

The Victorian Government is redeveloping and expanding the Frankston Hospital.
Project
Aerial artist impression shows hospital with trees and park nearby

27 June 2022

Design of bigger, better Frankston Hospital revealed

New designs reveal a first look at the largest ever health infrastructure investment in Melbourne’s south-east.
News
Frankston Hospital seen from the air

01 February 2022

Preferred bidder named for Frankston Hospital redevelopment

The bigger, better Frankston Hospital for families in Melbourne’s south-east is a step closer – with a preferred bidder named.
News
Last updated: 28 February 2023