Facebook icon
Hospitals 08 November 2024

First tower crane comes down on Frankston Hospital redevelopment site

The first of four tower cranes on the Frankston Hospital redevelopment site has been taken down, as the redevelopment enters its final year of construction.

The crane was the first to arrive on the site in March 2023. Capable of hoisting up to 14 tonnes of materials at a time, the crane supported major structural works on the new multi-deck carpark and eastern side of the new hospital tower.

The space left behind by the crane will now be filled in with concrete slabs, making way for internal works to be finished.

The remaining three tower cranes will be taken down progressively when they’re no longer needed, and as the project shifts its focus from the remaining external works to internal fit-out and finishing works.

How we disassembled the first tower crane

Weighing around 138 tonnes, the process to take down the first tower crane on the redevelopment site required a coordinated approach. The crane crew pays special attention to keeping everything balanced, only undoing bolts and pins when each section is safely rigged and weighted.

The process:

  1. The tower crane was taken down piece by piece by another crane on the site. (When there’s no other crane close by, often a mobile crane will be temporarily set up to help with dismantling.)
  2. The jib was lowered horizontally to its lowest turning radius. The jib is the long arm extending out from the crane which carries the load.
  3. For this crane, the jib was split into two pieces and each piece lifted to the ground separately.
  4. The various components of the crane, including the hoist drum and power pack, were then lifted down.
  5. We continued to remove the components on the deck, including the A-frame. The A-frame is a structure used for leverage, allowing tower cranes to lift heavier weights.
  6. The ‘towers’ (which are what gives the tower crane its height) were then lifted down, one section at a time.
  7. Finally, all the components were loaded into trucks waiting on the ground and then transferred off-site, ready for the next build.

What else is happening on-site

The new short stay unit in the emergency department is now complete and open. The façade is nearing completion with more than 4,000 façade panels installed on the new hospital tower and multi-deck carpark. And internal works are continuing, with 21 kilometres of fire sprinkler pipes installed.

Since work first started on-site in June 2022, the project has had more than:

  • 1.6 million hours of work carried out
  • 40,000 cubic meters of concrete poured
  • 195 tonnes of structural steel installed.

Main works on track to be completed late 2025.

Learn more about the Frankston Hospital redevelopment.

Related content

A model hospital redevelopment built out of cardboard and paper

24 October 2024

Connecting kids to the Frankston Hospital redevelopment

Dr Loz visited St Francis Xavier Primary School to engage students on the Frankston Hospital redevelopment happening across the road from their schoolyard.
Video
Illustration of male construction worker holding a wooden beam on his shoulder

12 September 2023

Frankston Hospital redevelopment newsletters

Read every issue of the Frankston Hospital redevelopment e-newsletters.
Newsletter
An aerial view of the exterior of Frankston Hospital, with cranes and scaffolding visible

23 July 2024

Frankston Hospital redevelopment hits maximum height

The Frankston Hospital redevelopment has reached structural completion, with the new clinical services hospital tower 'topping out' at 13 levels.
News
Last updated: 12 November 2024