Hospitals 12 December 2024

Frankston Hospital redevelopment façade complete

The impressive façade of the $1.1 billion Frankston Hospital redevelopment’s new clinical services tower is complete.

More than 4,000 glass, terracotta, and porcelain panels, each weighing between 250 to 1,000 kilograms have been carefully craned into place. The façade’s design allows for sunlight to flood into patient rooms and reflects the natural beauty of the Mornington Peninsula.

Construction of the emergency department’s new paediatric zone and mental health, alcohol and other drugs hub is also well underway, with staff and patients already benefiting from a newly completed short stay unit and updated treatment bays.

Onsite activity:

  • The workforce has reached its peak, with more than 1.8 million hours worked by about 3,800 people since construction began in June 2022
  • Solar panels are being installed, and a helipad is under construction at ground level, ready to be lifted onto the roof in stages
  • Interior fit out, including the installation of walls, plastering, and services, is progressing floor by floor.

Once complete, the massive redevelopment will transform services at the hospital and have capacity for 35,000 additional patients to be treated each year.

Frankston Hospital redevelopment façade is now complete

[Images: Aerial views of the hospital]

[Text on screen: The external façade on your bigger, better Frankston Hospital is complete!]

[Images: Timelapse footage of the hospital being constructed]

[Text on screen: The façade was carefully designed with glass, terracotta and porcelain to let sunlight flood in and to reflect the natural materials of the Peninsula]

[Images: Timelapse footage of the hospital being constructed]

[Text on screen: The striking exterior is made up of 4,458 panels, each weighing between 250 and 1,000 kgs]

[Images: Timelapse footage of the hospital being constructed]

[Images: The redevelopment’s workforce has reached its peak, with about 900 people on site each day]

[Text on screen: On track for completion in 2025]

[Images: Aerial views of the hospital]

[Images: A screen displays the text “In partnership with” and the Peninsula Health and Exemplar Health logos. A sliding transition screen then displays the Victorian Health Building Authority and Victoria State Government logos and the url vhba.vic.gov.au]

[End of transcript]

Learn more about the Frankston Hospital redevelopment by visiting our dedicated project page.

Related content

View of tower cranes framing the Frankston Hospital redevelopment construction site

08 November 2024

First tower crane comes down on Frankston Hospital redevelopment site

The first of four tower cranes on the Frankston Hospital redevelopment site has been dismantled.
News
A model hospital redevelopment built out of cardboard and paper

24 October 2024

Connecting kids to the Frankston Hospital redevelopment

Dr Loz visited St Francis Xavier Primary School to engage students on the Frankston Hospital redevelopment happening across the road from their schoolyard.
Video
Aerial view of Frankston Hospital at sunrise, taken by local photographer Steve Brown

16 August 2024

Frankston Hospital redevelopment - Newsletter #5 | August 2024

Welcome to our winter 2024 Frankston Hospital redevelopment newsletter. Learn about the crane crew, site progress and what’s happening next.
Newsletter
Last updated: 12 December 2024