Transcript
IMAGES: Opening time-lapse footage (high speed) taken from a webcam positioned high enough to look down to the base of the demolished infill building as workers and various machines remove bricks and debris.
TEXT: The final concrete was poured at the Eye and Ear Hospital redevelopment last month.
IMAGES: The time-lapse continues and workers are now laying ground floor concrete slab using a pump hose and long-handed bull floats (poles with flat trowels attached).
IMAGES: The screen splits into two frames. The left frame shows time-lapse footage of a pump hose and the right frame shows a close up of a worker in high vis operating a mechanical trowel.
TEXT: More than 3,300 cubic metres of concrete, 500 tonnes of steel reinforcement and 2,500 workers are responsible for getting the redevelopment to this point.
IMAGES: The high speed time-lapse vision continues to show the levels of the new building rise and workers using concrete laying tools for each level.
IMAGES: The screen splits into two and then three frames, each with different vision and variously showing close ups of the metal form work, workers levelling concrete using screeds, concrete trucks arriving at site and pouring their mix from buckets.
TEXT: Once operational, the lower levels will treat patients and the upper levels will be used for teaching, training and research.
IMAGES: Time-lapse vision shows workers directing concrete buckets over the form of the final floor and levelling with screeds.
IMAGES: The closing image is of the hospital seen from Morrison Place – the new building is structurally complete and connects the two older wings of the hospital.
IMAGES: The screen transitions to blue. We see the Victorian Health and Human Services Building Authority logo, the web address vhhsba.vic.gov.au and the Victoria State Government logo.
End of transcript.